featured-image

North East Lincolnshire Council, in partnership with Equans, is set to begin its annual carriageway surface dressing programme in the coming weeks. The process involves applying a bitumen emulsion spray to the road, followed by a layer of stone chippings, which are spread and rolled into the existing road surface. This seals the surface from water, improves texture, and extends the road's lifespan.

Once treated, vehicles can use the surface immediately. Each street will also undergo a second treatment about 10 days after the first. This additional step aims to secure the stone chippings into the new road surface, reducing any loose material.



Read more: Get the latest breaking news and top stories on WhatsApp Keep up to date with all the latest breaking news and top stories from Grimsby with our free newsletter The works are scheduled to start on Tuesday 28 August 2024 and should be completed by Sunday 01 September 2024. However, as these works are weather-dependent, dates may change. All affected residents have been notified via letter.

To ensure the safety of workers and allow for the completion of the works, a full road closure will be in effect from 7.30am to 6pm each day. Work may not take the entire day to finish, depending on the length of the street.

During the works, on-street parking will be temporarily suspended within the closure extents. Residents are asked to support the contractor by refraining from parking vehicles on the carriageway or footway in the works location. This ensures a safe working area can be maintained and helps avoid any delays to the works programme.

If you need to use your vehicle during the day when the road closure is in place, the council is urging people to make sure it is moved to an appropriate location outside of the closure area before the road closure begins. If you have a holiday planned during the construction period, you should ensure your vehicle is parked on your drive or at an appropriate location outside of the closure area. If the works are delayed due to parked vehicles, additional days of road closures will be required to enable the works to be completed.

Pedestrian access will be maintained at all times. Access for emergency vehicles will be maintained throughout the works. In order to ensure the effectiveness of the surface treatment, the contractor will also implement a road sweeping programme.

This includes three sweeps over a 30-day period to clear any surplus material. The contractor will return at the following times: Within 48 hours of the work completion. 7 to 10 days post-completion.

30 days after the works have been completed. The council are requesting that residents try to avoid parking on the street during these times to allow for the collection of as much excess material as possible. The sweeper will operate during daylight hours, but the council cannot provide a specific time or date.

Full list of streets 28 August: Elliston Street - From Grimsby Road to Brereton Avenue 28 August: Grainsby Ave - Full extent 28 August: Clerke Street - Full extent 28 August: Johnson Street - Full extent 28 August: Beacon Court - Full extent 28 August: Hamilton Street - Full extent 28 August: Rutland Street - Grafton Street and Cleethorpe Road 28 August: Mansel Street - Hamilton Street and Grafton Street 29 August: Stanley Street - From Oxford St to Cleethorpe Road 29 August: Grafton Street - From Stanley Street to Hilda Street 29 August: Cope street - From column 5 to end of road 29 August: Albert St East - Full extent 29 August: Albert St - West 29 August: Bath St - Full extent 29 August: Hope St - Full extent 30 August: Nelson St - From Railway Street to Freeman Street 30 August: Bedford St - Full extent 30 August: Bodiam Way - Full extent 30 August: Bradley St - Full extent 30 August: Harlech Way - Full extent 30 August: Werneth Rd - Full extent 30 August: Responso Ave - Full extent 30 August: Rialto Ave - From Heneage to Hainton 30 August: Rialto Ave - From Heneage to End (east) 31 August: Patrick St - From People's Park to Hainton Ave 31 August: Remillo Ave - Full extent 31 August: Tasburgh St - Full extent 31 August: Chiltern Way - Full extent 31 August: Southwold Crescent - Full extent 31 August: Mendip Avenue - From Quantock Road to Waltham Road 31 August: Oxcombe Close - Full extent 31 August: Fallowfield Road - At Springwood Cresecent - end only 01 September: Garibaldi Street - From Albion to Freeman 01 September: Duncombe St - Full extent 01 September: Wood St - Full extent 01 September: Newmarket St - Full extent Join the FREE Grimsby Live WhatsApp Community Get all the latest stories, sent straight to your WhatsApp - all you need to do is click the link . We also treat our community members to special offers, promotions, and adverts from us and our partners. If you don’t like our community, you can check out any time you like.